Side-by-side comparison
Choose which states to compare. On a phone, scroll the table sideways.
Showing:
| Pennsylvania | Virginia | Ohio | Maryland | Georgia | |
|---|---|---|---|---|---|
| Who sets the terms | |||||
| Regulator | Pennsylvania Public Utility Commission | State Corporation Commission | Public Utilities Commission of Ohio | Maryland Public Service Commission | Georgia Public Service Commission |
| Mechanism | Voluntary model tariff; each utility adopts it through its own tariff filing | New GS-5 rate class in Dominion Energy Virginia's rates | Data center tariff for one utility, approved as a settlement | Statute requires large-load tariffs; utility tariffs pending before the PSC | PSC rule allowing customized contracts for Georgia Power's largest customers |
| Utilities covered | All electric distribution companies, as guidance | Dominion Energy Virginia | AEP Ohio | BGE, Delmarva Power, and Pepco filed jointly; the statute also covers Potomac Edison | Georgia Power |
| Decision and date | Final order May 12, 2026 (Docket M-2025-3054271) | Final order Nov. 25, 2025 (Case PUR-2025-00058); effective Jan. 1, 2027 | Order July 9, 2025 (Case 24-508-EL-ATA); effective July 23, 2025 | Next Generation Energy Act (SB 937, Chapter 625), signed May 20, 2025, first required large-load rate schedules; Utility RELIEF Act (HB 1532), enacted May 12, 2026, lowered the thresholds; utility tariff filed Sept. 29, 2026 | Rule approved Jan. 23, 2025; effective Feb. 1, 2025 |
| Who it applies to | |||||
| Size threshold | Over 50 MW individually or 100 MW in aggregate; utilities may apply it below 50 MW | 25 MW or more | New or expanded data center load over 25 MW; mobile data centers over 1 MW | 25 MW aggregate monthly demand (lowered from 100 MW in the 2025 Next Generation Energy Act) | 100 MW or more |
| Load factor | Not specified in sources reviewed | 75% or more | Not specified in sources reviewed | 60% (lowered from over 80% in the 2025 Next Generation Energy Act) | Not specified in sources reviewed |
| What customers commit to | |||||
| Minimum bill | 80% of contract capacity | 85% of contracted transmission and distribution demand; 60% of contracted generation demand | Up to 85% of contract capacity, on a sliding scale by size | Pending PSC decision | Allowed; set contract by contract |
| Contract term | Load ramp period plus a minimum initial term of 5 years | 14 years | 12 years, including the load ramp | Pending PSC decision | Up to 15 years under the rule (previously 5); Georgia Power testified its contracts run 15 years or longer |
| Load ramp | Load ramp schedule set in the contract | Up to 4 years, adding at least 20% of contracted demand each year | 4 years | Pending PSC decision | Set in each contract |
| Exit terms | 48 months' notice for termination or major capacity reduction | Exit fees to recover remaining contract costs on early termination | Exit fee equal to three years of minimum charges, or three years' notice after the initial period | Pending PSC decision | Early termination penalties set in each contract |
| Collateral | Enough to cover network improvement and interconnection facilities costs; reduced or refunded as milestones are met | $1.5 million per MW of contracted demand, reducible by up to 70% for strong credit and released over the contract term | Customers below set credit standards post collateral equal to 50% of total minimum charges; surety bonds not accepted | Pending PSC decision | Letters of credit or other collateral, per Georgia Power testimony |
| Costs and oversight | |||||
| Costs assigned | Interconnection and infrastructure costs of serving the customer | Transmission, distribution, and generation, through minimum charges | Subscribed capacity, regardless of actual use | The PSC is directed to consider cost-allocation approaches for large-load customers. The 2025 act also lets the PSC assign specified costs to co-location arrangements in which a large customer takes power directly from a generating station without using the grid. | Upstream generation, transmission, and distribution costs, plus site-specific costs |
| Regulator review | PUC reviews each utility's tariff filing | Terms set in the utility's rate case | Approved by PUCO as a tariff | PSC hearings Oct. 23 and Dec. 8-11, 2026 | Contracts filed with the PSC at least 30 days before signing; quarterly reports on new large loads |
| Status and sources | |||||
| 2026 status | Model adopted; utilities adopting through their own filings. On Oct. 1, 2026, the PUC issued a tentative order (Docket M-2026-3064961) proposing that utilities identify and track large computational load customers and, during a PJM Interim Resource Adequacy Service (IRAS) action, shed load from those customers before any other customers. It proposes that data centers not be classified as critical load exempt from curtailment and asks for comment on how to define which customers should be barred from that classification. FERC rejected PJM’s IRAS proposal on Oct. 9, 2026, finding that the proposed tariff appeared to place obligations directly on retail customers and set a retail rate, and encouraged states to designate which retail customers are curtailed when the system is stressed. On Nov. 5, 2026, the PUC issued a clarification order saying it is no longer seeking comment on the pre-emergency curtailment provisions tied to IRAS, citing FERC’s decision; it still seeks comment on changes to utilities’ emergency load-control procedures. Comments are due 20 days after the clarification order is published in the Pennsylvania Bulletin, with reply comments due 30 days after publication (as reported). The PUC has targeted a final vote for Jan. 28, 2027 (as reported). Separately, on Oct. 15, 2026, the Governor petitioned to intervene in the PUC proceeding on the Office of Consumer Advocate’s complaint against PPL Electric Utilities’ rates (Docket C-2026-3065756), seeking a separate rate class for large data centers. HB 2828, which cleared the House Energy Committee in September 2026, would require utilities to adopt it. HB 2828 was laid on the table Sept. 30, 2026, and did not receive final votes before the session’s last voting day, Nov. 17, 2026 (as reported); it would need to be reintroduced in the 2027–28 session. | Approved; takes effect Jan. 1, 2027. In August 2026, the SCC ordered Dominion to develop a tariff assigning more transmission costs to data centers | In effect; Ohio Manufacturers' Association appeal pending at the Ohio Supreme Court. AEP Ohio's tariff will serve the initial 800 MW phase of SoftBank's Flagship data center project in Pike County. At Ohio's request, PJM filed a study agreement at FERC on Oct. 13, 2026 to study the remaining 9.6 GW under its state agreement approach, with cost allocation left to future PUCO and FERC proceedings (as reported). Substitute HB 646 would create a statewide data center rate class. Duke Energy Ohio has proposed a separate Data Center Tariff (Rate DC) in PUCO Case No. 26-0755-EL-ATA; PUCO staff filed comments in October 2026, and no decision has been issued (as reported). | Statute in effect; tariff terms pending | In effect; Nov. 3, 2026 PSC elections: Peter Hubbard re-elected in District 3 and Shelia Edwards elected in District 5 (unofficial results) (as reported). On July 7, 2026, the PSC unanimously approved an investigation into whether Georgia Power's pricing for data centers and other large customers shifts costs to residential customers; it is set to be completed by the end of 2026 (as reported). |
| Still to verify | Nothing outstanding | Nothing outstanding | Nothing outstanding | Terms proposed in the Sept. 29 utility filing; whether Potomac Edison has filed | Early termination terms in practice |
| Sources | puc.pa.govpuc.pa.govwomblebonddickinson.comabc27.comutilitydive.compuc.pa.govpa.govFERC order, PJM Interconnection, L.L.C., 197 FERC ¶ 61,019, Docket ER26-3515-000 (Oct. 9, 2026)utilitydive.comfirstnewsnowpa.comenergychoicematters.compuc.pa.gov | scc.virginia.govscc.virginia.govvirginiamercury.comutilitydive.comwhro.orgaxios.com | aepohio.compowermag.comohiocapitaljournal.comutilitydive.comeei.org | utilitydive.comgfrlaw.comdailyenergyinsider.comchestertownspy.orgmgaleg.maryland.govmgaleg.maryland.gov | datacenterdynamics.comgovtech.comcomputelaw.blogcleanenergy.orgroughdraftatlanta.comroughdraftatlanta.com |
| Last updated | 2026-11-20 | 2026-10-23 | 2026-11-10 | 2026-10-29 | 2026-11-11 |
What stands out
Five states, five ways of setting terms
Virginia created a rate class in a utility rate case. Ohio approved one utility's tariff as a settlement. Pennsylvania issued a voluntary model for each utility to adopt. Maryland set the threshold by statute and left the terms to pending tariff cases. Georgia allows custom contracts, each reviewed by the commission before signing.
Where terms are written, they look alike
Minimum bills cluster at 80 to 85 percent of contracted demand, with Virginia setting 60 percent for generation. Contracts run 12 to 15 years, and collateral for customers without strong credit runs about half of minimum charges. Pennsylvania's model is the outlier on length, with a five-year minimum after the ramp period and 48 months' notice to exit.
Thresholds vary more than terms
Virginia, Ohio, and Maryland start at 25 MW. Pennsylvania starts at 50 MW individually or 100 MW in aggregate, and Georgia at 100 MW. The same project can fall under very different rules depending on where it is built.
Legislatures are moving into space regulators built
Pennsylvania's HB 2828 would have required utilities to adopt the commission's model; it didn’t receive final votes before the 2025–26 session ended. Maryland's statute already sets the threshold. Ohio's Substitute HB 646 would create a statewide data center rate class, and a Georgia Senate committee heard testimony this year on a bill to codify the commission's protections.
What to watch
- After November 3, 2026: Ohio's Substitute HB 646 is expected to return; the Ohio Supreme Court appeal of AEP Ohio's tariff is pending.
- November 5, 2026: public testimony begins on NextEra's proposed acquisition of Dominion Energy, followed by the SCC's evidentiary hearing November 17 and a decision due by January 11, 2027. On October 19, SCC staff recommended denial unless the companies accept binding conditions, and supported a residential bill credit that data centers would not receive. The same day, Gov. Spanberger's testimony asked for a six-year residential base-rate freeze, $29 monthly bill credits for four years, and stronger protections against data center costs being passed to households, including a separate company to build clean energy for large data centers.
- December 8-11, 2026: Maryland PSC hearings on the BGE, Delmarva Power, and Pepco large-load tariff.
- January 2027: Pennsylvania’s new legislative session begins; 2025–26 data center bills would need to be reintroduced.
- January 1, 2027: Virginia's GS-5 rate class takes effect, with a separate transmission cost tariff still in development.
- January 28, 2027: PUC final vote targeted on emergency curtailment rules for large loads (as reported).
- March 1-28, 2027: PJM's proposed bid window for its reliability backstop procurement. Under PJM's Oct. 29, 2026 amended filing, costs would be assigned to each zone based on its share of firm large-load growth reported by electric distribution companies; how those charges reach retail customers is a state question. Details on the screening page.
- Federal: whether the Senate passes the Bipartisan American Affordability and Jobs Act (H.R. 2347 as the vehicle), which it voted 73–25 to begin debating on Nov. 9, 2026. As introduced, Section 2107 would require transmission service for computational loads to cover both embedded and incremental costs, require loads of 20 MW or more to pay the full incremental cost of service with financial assurances, and confirm states' authority to set separate rates or require new generation (as reported).
- Pending: PA PUC technical conference on large computational load cost allocation, postponed Oct. 28, 2026; new date to be set.
The question I expect to shape the next round: whether large-load terms stay with regulators, set utility by utility, or move into statute, trading flexibility for uniformity.